In Pictures...
 

11/11/02
Contractors move on site

03/12/02
Demolition Begins

20/12/02
Demolition almost complete

           

10/01/03
Construction work begins

26/03/03
Final Stages of demolition

09/05/03
Construction well under way

           

19/05/03
Bridge structures start to appear

04/06/03
Construction of seaward & promenade abutments.

19/06/03
Bridge pier and road surface.

           

10/07/03
Bridge pier getting near the top.

04/08/03
Views of the construction site form roof of Funland

19/08/03
Views from the construction site.

           

22/09/03
Bridge surface and pier

24/09/03
Pier top piece put in place

14/10/03
from one side to the other.

           

21/11/03
1 year on.

22/01/04
Cable, Scaffold & Road

05/02/04
We have lift off

           

09/03/04
Views of the road surface from Funland.

30/03/04
Joining the lake and top of the pier

31/03/04
Something is casing a stir

           

01/04/04
New signage moved in place on bridge

08/04/04
Water under the bridge

13/04/04
Views from on the bridge

           

22/04/04
Views from Funland

11/05/04
Just 3 days to go before the opening of The Marine Way Bridge

14/05/04
The bridge is officially opened

           

14/05/04
Watch the bridge change from the old bridge in to the new one

15/05/04
Views from the bridge last night on its first night of opening

19/07/04
The Earl and Countess of Wessex at the Royal Opening of the bridge

.          